Question
I have a party wall agreement with my neighbour and have started my building project however it is likely to overrun the 12 month period the Award covers. What should I do about this? Can I just continue work as before?
Answer
The 12 month period is only the time after the notice date after which your works must commence. So long as the works are carried through with reasonable expedition after commencement so as to avoid unnecessary inconvenience to the adjoining owner or occupiers you will be fine.
Categories: Party Wall Awards